Extension activities during the year,
2014-2015:-
1)
Renovation of
public well at Bualpui village:-Renovation
of Public well at Bualpui village, one of the dopted villages, was carried out
on the 28th March, 2014. 137 NSS volunteers (students) along with
the PO’s of the NSS unit worked from 10:00 am till 4:30 pm.
2)
Construction
of public urinal and toilet at Bualpui village:- Public urinal and toilet were constructed at
Bualpui. 200 odd student- volunteers and the PO’s of the NSS unit worked for
two days during 12th – 13th December, 2014.
3)
Renovation of
public well at Rengtekawn village:- Rengtekawn
is another adopted village where 135 volunteers and PO’s of the NSS unit did a
renovation work on the public well on the 13th June, 2015.